Fabrication and Machining Cost Calculator
Price per part and batch total from material, machine time, labour and overheads.
Build a quick, transparent cost estimate for a fabricated or machined part. Enter raw material weight and rate with a scrap allowance, machining and labour hours with their rates, finishing, batch setup cost, overhead and profit margin.
- Live results
- Full step-by-step working
- PASS / FAIL checks
- Free PDF report
Results
Step-by-step calculation (9 steps)
- 1Material cost per partFormulaCm = W·(1 + s)·cmSolutionCm = 12 × (1 + 0.1) × 85ResultCm = ₹ 1122.00
- 2Machining cost per partFormulaCmc = tm·rmSolutionCmc = 1.5 × 900ResultCmc = ₹ 1350.00
- 3Labour cost per partFormulaCl = tl·rlSolutionCl = 2 × 350ResultCl = ₹ 700.00
- 4Setup cost per partFormulaCs = setup / NSolutionCs = 2000 / 10ResultCs = ₹ 200.00
- 5Direct cost per partFormulaCd = Cm + Cmc + Cl + Cf + CsSolutionCd = 1122.00 + 1350.00 + 700.00 + 400.00 + 200.00ResultCd = ₹ 3772.00
- 6OverheadFormulaCo = o·CdSolutionCo = 0.15 × 3772.00ResultCo = ₹ 565.80
- 7Profit and selling price per partFormulaPrice = (Cd + Co)·(1 + p)SolutionPrice = 4337.80 × (1 + 0.15)ResultPrice = ₹ 4988.47 per part
- 8Batch totalFormulaTotal = Price·NSolutionTotal = 4988.47 × 10ResultTotal = ₹ 49884.70
- 9Cost split (direct cost)Formulashare = item / CdSolutionmaterial : machining : labour : finishing : setupResult29.7% : 35.8% : 18.6% : 10.6% : 5.3%
Engineering takeaways
- The largest cost driver is machining (35.8% of direct cost). Design changes should target it first.
- Setup cost is spread over the batch: doubling the quantity halves setup cost per part.
- This is an order-of-magnitude estimate. Tolerances, inspection, heat treatment, transport and supplier rates can move the final price by 20 to 40%.
The PDF report contains every input, formula, substitution and check shown above, in LTM calculation-sheet format.
Worked Example
The calculator shows each cost element, the selling price per part, the batch total and the largest cost driver, in Indian rupees, US dollars or euros.
The calculator above opens with this example. Change any input to run your own case.
Inputs
| Currency | INR ₹ |
|---|---|
| Batch quantity | 10 pcs |
| Raw material weight per part | 12 kg |
| Scrap and cutting allowance | 10 % |
| Material rate | 85 per kg |
| Machining hours per part | 1.5 h |
| Machine hour rate | 900 per h |
| Fabrication / labour hours per part | 2 h |
| Labour rate | 350 per h |
| Finishing / painting per part | 400 per part |
| Setup and programming cost per batch | 2000 per batch |
| Overhead | 15 % |
| Profit margin | 15 % |
Results
| Price per part | ₹ 4988.47 |
|---|---|
| Batch total (10 pcs) | ₹ 49884.70 |
| Direct cost per part | ₹ 3772.00 |
| Largest driver | machining |
Fabrication Cost Formulas Used
Direct cost per part
- Wraw material weight
- sscrap allowance
- tm, rmmachine hours and rate
- tl, rllabour hours and rate
- Nbatch quantity
Selling price
- ooverhead fraction
- pprofit margin fraction
Batch total
Basis: Standard job costing method (direct cost + overhead + margin). Results are for preliminary design and should be confirmed against supplier data and the governing standard.
Fabrication Cost Calculator FAQ
How do I estimate fabrication cost?
Add material cost (weight × rate, plus scrap), machine time × machine hour rate, labour time × labour rate, finishing and a share of setup cost. Apply overhead and profit on top.
What scrap allowance should I use?
Use 5 to 10% for plate and bar cut close to size, and 15 to 30% for parts machined from solid or nested profiles with large offcuts.
Why does batch size change the price?
Setup, programming and first-off inspection are one-time costs per batch. Spreading them over more parts lowers the price per part.
What machine hour rate is typical in India?
Rates vary widely by machine and region. Conventional machines may be a few hundred rupees per hour, while VMC and HMC work often runs from about ₹800 to ₹2000 per hour. Use quotes from your own suppliers.
How accurate is this estimate?
It is an order-of-magnitude estimate for budgeting and design comparison. Tolerances, inspection, heat treatment, coating and transport can move the final price by 20 to 40%.